PSA: If you’re heading to the airport over January to early March 2025, we encourage you to allow an extra 30 minutes for your journey due to potential delays caused by construction works in the Terminal 123 forecourt. If you're picking up or dropping off loved ones, consider using Exit 19A and the Terminal 4 Car Park to avoid congestion in the Terminal 123 forecourt. We apologise for the inconvenience.

Sewerage Connection

Overview

Melbourne Airport own, operate and maintain its own embedded sewer network within its precinct boundaries.

Connection into Melbourne Airport sewer network is an integral step in managing the wastewater discharge from the subject site.  All connections and modifications to the network must satisfy MRWA, WSAA and Melbourne Airport standards and regulations and be accordance with the precinct masterplan.

How to apply for a permit

  1. Complete the Sewer Connection application and ensure:

    a. A sketch/drawing indicating location of proposed connection into APAM sewer asset is provided
  2. Email completed form to APAM Civil team via [email protected]
  3. Application on approval will be returned to applicant

Download the application form by clicking here.